Our Facility

God has given us a wonderful facility which is still under construction. We expect to have temporary occupancy of our classrooms and offices by the second half of October 2018 and plan to have complete occupancy in November. Here is what is happening this week (October 15-21); concrete sidewalks and ramps may be poured as early as Wednesday, drywall in the sanctuary and gym is being taped and textured, A/V techs are taking measurements for all their equipment, offices and office hall flooring will be installed this weekend and we are continuing to paint the facility. Lighthouse Baptist School is also beginning to get all their classrooms read for students to occupy hopefully next week. Please pray that we will get our plans approved promptly by the city for our baptistry.